Plant supplier updates the schedule of OL3 project
8.11.2019
The plant supplier Areva-Siemens Consortium will perform a schedule review and provide Teollisuuden Voima Oyj (TVO) by an overall rebaseline schedule for the final phases of the project in December.
According to the plant supplier’s schedule provided in July, nuclear fuel was planned to be loaded into the reactor in January 2020, the first connection to the grid was planned to take place in April 2020, and the start of regular electricity production of the OL3 EPR nuclear power plant unit was planned to take place in July 2020.
- Although, the completion of the plant unit will be further delayed, we are very close to reach the fuel loading phase and start-up of the OL3 EPR unit. TVO is currently preparing fuel loading application, says Jouni Silvennoinen, TVO's Director of the OL3 EPR Project.
OL3 plant supplier consortium is constructing the plant unit under a fixed-price turnkey contract. The supplier consortium companies, AREVA GmbH, AREVA NP SAS and Siemens AG, have joint and several liability for the contractual obligations until the end of the guarantee period of the plant unit.
For further information, please contact:
Jouni Silvennoinen, Senior Vice President, OL3 Project
Interview requests:
Pasi Tuohimaa, Communications Manager
tel: +358 40 544 5001