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
Update: Annual outage of OL3 completed by May 8th
28.4.2024
The first-ever outage of Olkiluoto 3 will be extended by four days due to technical issues. According to the updated schedule, the outage will now be completed by May 8th.
The annual outage of OL3 started on March 2. Approximately 1,100 external professionals are involved in the outage.